File #: 18-1764    Version: Name: Frederick Douglass Gym Closeout
Type: Resolution Status: Passed
File created: 1/31/2018 In control: City Commission
On agenda: 3/6/2018 Final action: 3/6/2018
Title: *Approving final closeout reconciliation to D.L. Porter Constructors, Inc. in an amount not to exceed $93,758.88 for unforeseen conditions and additional work required for the Frederick Douglass Community Center Project; Authorizing a time extension of 130 calendar days for substantial completion of the project (to January 14, 2018); Authorizing necessary budget transfers/amendments; Authorizing the City Manager to execute necessary documents.
Sponsors: Jim Scholl
Attachments: 1. Resolution, 2. Executive Summary, 3. Change Order Request No. 8, 4. Change Order Request No.12, 5. Change Order 8 (Final), 6. *Large File* Resolution 16-198

Title

*Approving final closeout reconciliation to D.L. Porter Constructors, Inc. in an amount not to exceed $93,758.88 for unforeseen conditions and additional work required for the Frederick Douglass Community Center Project; Authorizing a time extension of 130 calendar days for substantial completion of the project (to January 14, 2018); Authorizing necessary budget transfers/amendments; Authorizing the City Manager to execute necessary documents.