File #: 18-2239    Version: Name:
Type: Resolution Status: Passed
File created: 5/4/2018 In control: City Commission
On agenda: 6/5/2018 Final action: 6/5/2018
Title: *Approving Task Order No. 4-18-SWR from CH2M Hill Engineering, Inc. in an amount not to exceed $299,629.92 for the Design, Permitting, Bid Phase and Construction Phase Services for the Rehabilitation of Pump Stations “C” and “E”; Authorizing the City Manager to execute any necessary documents upon consent of the City Attorney.
Sponsors: Jim Scholl
Attachments: 1. Resolution, 2. Executive Summary, 3. Task Order 4-18 SWR, 4. Resolution 17-207, 5. CH2M Hill Engineering Services Agreement

Title

*Approving Task Order No. 4-18-SWR from CH2M Hill Engineering, Inc. in an amount not to exceed $299,629.92 for the Design, Permitting, Bid Phase and Construction Phase Services for the Rehabilitation of Pump Stations “C” and “E”; Authorizing the City Manager to execute any necessary documents upon consent of the City Attorney.