13-4309
| 1 | 3 | | Discussion Items | Swearing-in of Witnesses to Testify | | |
Action details
|
Not available
|
15-8496
| 1 | | | Action Items | MINUTES September 16, 2015 | Approved | Pass |
Action details
|
Not available
|
15-8478
| 1 | | | Action Items | 15CEB70 T RYAN CONTRACTING INC (hearing)
Code Officer Leonardo Hernandez
704 Caroline Street
CHARGE: Working without benefit of a building permit and Certificate of Appropriateness (HARC).
On 6/23/15 contractor was found working at site (removed deck to access roof).
PERMIT APPLICATION: | Approved | Pass |
Action details
|
Not available
|
15-8480
| 1 | | | Action Items | 15CEB71 STONE AGE CONSTRUCTION INC (hearing)
Code Officer Bonnita Badget
26 Kestral Way
CHARGE: Working without benefit of a building permit.
On 9/2/15 Officer Badget wrote "I placed a stop-work-order at 26 Kestral Way for replacing 3 windows and trim. Stonage Construction, Michael Posada. "
PERMITS: Permit 15-3936 was applied for on 9/21/15 and picked up on 9/30/15. Applicant was Wayne Garcia CBC.
Application number . . . . : 15 00003936
Address . . . . . . . . . : 26 KESTRAL 236
DESC 9/21/15 Y AFTER THE FACT: 14-37 BUILDING JAM
DESC 9/21/15 Y WINDOWS(3)REPLACE ON DECAL FLOOR WHITE
DESC 9/21/15 Y TRIM. NOTE:STOP WORK ORDER BY BONITA
DESC 9/21/15 Y CODE OFFICER. NOC EXEMPT.
DESC 9/21/15 Y T/S:09/21/2015 11:41 AM KEYWGRC --- | Approved | Pass |
Action details
|
Not available
|
15-8479
| 1 | | | Action Items | 15CEB75 SALINERO ENTERPRISES (hearing)
Building Inspector David Ray
3743 Donald Avenue
CHARGE: Depart from or disregard in any material respect the plans or specifications of a construction job without consent of owner or authorized representative.
On August 5, 2015 the Building Department received a request from the DBPR Construction Industry Licensing Board to investigate a pool installation complaint at 3743 Donald Avenue.
David Ray visited the site and found that:
1. Pool is not level (Between 4" and 4 1/2" difference end to end.)
2. Wet deck around pool cracked.
3. The Hayward salt generator was incorrectly installed according to manufacturer technician.
PERMIT APPLICATION: On 5/2/14 pool permit was applied for and issued 5/22/14.
Application number . . . . : 14 00001983
Address . . . . . . . . . : 3743 DONALD
DESC 5/02/14 Y INSTALL A 13' X 29' FIBERGLASS POOL | Approved | Pass |
Action details
|
Not available
|
15-8482
| 1 | | | Action Items | 15CEB72 AMCON GROUP INC (hearing)
Code Officer Bonnita Badget
404 Duval Street
CHARGE: Working without benefit of a building permit.
On 10-8-15 Officer Badget placed a stop-work-order at 404 Duval Street for contractor installing drywall without a permit; contractor license was expired. Flooring was being installed by unlicensed workers.
PERMIT: Permit applied for on 10-13-15, approved on 10/27/15, but was not picked up as of 11/4/15.
Application number . . . . : 15 00004250
RE #/PARCEL #/TAX ID etc . : - - - -
Address . . . . . . . . . : 404 DUVAL
Type information, press Enter.
2=Change 4=Delete 5=Display
Opt Code Date Print Miscellaneous Information
DESC 10/13/15 Y AFTER THE FACT:THIS PERMIT IS FOR | Approved | Pass |
Action details
|
Not available
|
15-8484
| 1 | | | Action Items | 15CEB73 Wardlow Building Group Inc. (hearing)
Code Officer Bonnita Badget
3800 Duck Avenue
CHARGE: Working without benefit of permit (pool electrical and building).
On 9/1/15 Officer Badget issued a stop-work-order at 3800 Duck Avenue after the licensed and permitted electrical contractor (JC Electric) cancelled his permit and pulled off the job due to someone else completing
the electrical work under his permit. While on the site she also saw that a deck was under construction and the deck permit was not issued.
ELECTRICAL PERMITS:
Original pool electrical permit:
Application number . . . . : 15 00002914
Address . . . . . . . . . : 3800 DUCK
DESC 7/15/15 Y PROVIDE ELECTRICAL BONDING AND FINAL
DESC 7/15/15 Y ELECTRICAL CONNECTIONS FOR NEW POOL
DESC 7/15/15 Y BEING CONSTRUCTED. SEE POOL STRUCTURAL | Approved | Pass |
Action details
|
Not available
|
15-8497
| 1 | | | Discussion Items | Proposed meeting dates 2016 | Received and Filed | |
Action details
|
Not available
|