File #: 13-4196    Version: Name: Approve Task Order # 14 to Atkins NorthAmerica for CEI & monitoring for Smathers Beach Phase II
Type: Resolution Status: Passed
File created: 4/12/2013 In control: City Commission
On agenda: 6/4/2013 Final action: 6/4/2013
Title: *Authorizing the award of Task Order No. 14 for Construction Engineering & Inspection (CEI) and Four-Year Post Construction Biological and Physical Monitoring for the Renourishment of Smathers Beach Project Phase II to Atkins North America, Inc. (“Atkins”) in an amount not to exceed $193,609.00; Authorizing necessary budget transfers.
Sponsors: Bob Vitas
Attachments: 1. Resolution, 2. Executive Summary, 3. Task Order 14, 4. Resolution 11-090
Title
*Authorizing the award of Task Order No. 14 for Construction Engineering & Inspection (CEI) and Four-Year Post Construction Biological and Physical Monitoring for the Renourishment of Smathers Beach Project Phase II to Atkins North America, Inc. ("Atkins") in an amount not to exceed $193,609.00; Authorizing necessary budget transfers.