File #: 13-3899    Version: 1 Name: Authorize a thirty (30) day extension to the contract with D.N. Higgins, Inc. for the Glynn Archer Drive Sidewalk Enhancement Project No. EN-1004. The original contract time was 150 days with a 90 day extension for a contract completion date of February
Type: Resolution Status: Passed
File created: 1/28/2013 In control: City Commission
On agenda: 2/5/2013 Final action: 2/5/2013
Title: *Authorizing an additional thirty (30) day contract time extension for Douglas N. Higgins, Inc., to complete construction of the Glynn Archer/14th Street Roadway Reconstruction (Project No. EN-1004) at no additional cost.
Sponsors: Bob Vitas
Attachments: 1. Resolution, 2. Executive Summary, 3. Extension Request
Title
*Authorizing an additional thirty (30) day contract time extension for Douglas N. Higgins, Inc., to complete construction of the Glynn Archer/14th Street Roadway Reconstruction (Project No. EN-1004) at no additional cost.