File #: 10-868    Version: Name: Change order to Utility Design task order - FDOT
Type: Resolution Status: Passed
File created: 11/11/2010 In control: City Commission
On agenda: 12/7/2010 Final action: 12/7/2010
Title: *Approving an increase of $22,009.22 to the Utility Design by FDOT Consultant Agreement originally approved in City Commission Resolution 09-102 to permit an extension of the project to 14th Street; Providing for necessary budget transfers.
Sponsors: Jim Scholl
Attachments: 1. Resolution, 2. Executive Summary, 3. Additional Design Cost Estimate, 4. Original FDOT JPA - North Roosevelt Design, 5. Fully Executed JPA Design

Title

*Approving an increase of $22,009.22 to the Utility Design by FDOT Consultant Agreement originally approved in City Commission Resolution 09-102 to permit an extension of the project to 14th Street; Providing for necessary budget transfers.