File #: 25-3400    Version: 1 Name: Work Change Directive 1 to add Bid Phase Services to Task Order 11-23 Pump Station F Grinder Installation professional services from Jacobs Engineering Group in the amount of $8,922.00
Type: Resolution Status: Passed
File created: 2/14/2025 In control: City Commission
On agenda: 3/4/2025 Final action: 3/4/2025
Title: *Approving Amendment 1 to Task Order 11-23 for Jacobs Engineering Group, Inc. in an amount not to exceed $8,922.00 to add bid phase services for installation of a grinder at wastewater Pump Station F; Authorizing any necessary budget transfers and adjustments; Authorizing the City Manager to execute any necessary documents upon consent of the City Attorney.
Sponsors: Brian L. Barroso
Attachments: 1. Resolution, 2. Cover Memo, 3. Change Order, 4. Amendment #1 for Bid Phase Services, TO 11-23 Pump Station F Grinder Installation, rev 2-14-2025, Jacobs, 5. Resolution 24-078 / TO 11-23, 6. Resolution 23-029, 7. Jacobs Engineering Group contract

Title

*Approving Amendment 1 to Task Order 11-23 for Jacobs Engineering Group, Inc. in an amount not to exceed $8,922.00 to add bid phase services for installation of a grinder at wastewater Pump Station F; Authorizing any necessary budget transfers and adjustments; Authorizing the City Manager to execute any necessary documents upon consent of the City Attorney.