File #: 12-3114    Version: 1 Name: Extending the Contract for Lanzo Construction Co. on the Patricia and Ashby Streets Stormwater Emergency Outfall Project to December 7, 2012 on a No-Cost Basis
Type: Resolution Status: Passed
File created: 8/2/2012 In control: City Commission
On agenda: 8/21/2012 Final action: 8/21/2012
Title: *Extending the Contract for Lanzo Construction, Inc. for the construction of the Patricia/Ashby Street Stormwater Emergency Outfall Project to December 7, 2012 on a no-cost basis.
Sponsors: Bob Vitas
Attachments: 1. Resolution, 2. Executive Summary, 3. Contractor Lanzo Construction Co. Request for 60 Day Time Extension, 4. Project Engineer of Record Letter of Support for No-Cost Extension, 5. Resolution 11-347
Title
*Extending the Contract for Lanzo Construction, Inc. for the construction of the Patricia/Ashby Street Stormwater Emergency Outfall Project to December 7, 2012 on a no-cost basis.