File #: 2017-819    Version: 1 Name: Change Order 6 to D L Porter for Spalling and structural repairs at Frederick Douglass Recreation Center
Type: Resolution Status: Passed
File created: 6/5/2017 In control: City Commission
On agenda: 6/6/2017 Final action: 6/6/2017
Title: *Approving Change Order No. 6 to D. L. Porter Constructors, Inc. in an amount not to exceed $250,007.93 for unforeseen spalling and structural repairs at the Frederick Douglass Community Center Project, as an emergency procurement pursuant to Section 2-797(2) of the Code of Ordinances; Authorizing a Waiver of Code of Ordinances Section 2-845, to authorize the City Manager to allocate up to $30,000.00 of contingency allowance as necessary; Authorizing necessary budget transfers/amendments; Authorizing the City Manager to execute necessary documents.
Sponsors: Jim Scholl
Attachments: 1. Resolution, 2. Executive Summary, 3. Change Order No. 6 Spalling Repair, 4. Change Order Revised #10R - Spalling Repairs Revised, 5. RFQ 17-001 Architecture Evaluation Form-FILLED., 6. Shift Frederick Douglass Concrete Restoration, 7. Bella Douglass Gym Concrete Repair Cost Proposal, 8. Schnell Contractors Douglass Gym Concrete Repair Cost Proposal, 9. M13178 Fredrick Douglass Gym Repair Recommendations 5.11.2017, 10. *Large File* 2013 Structural Assessment, 11. *Large File* Resolution No. 16-198

Title

*Approving Change Order No. 6 to D. L. Porter Constructors, Inc. in an amount not to exceed $250,007.93 for unforeseen spalling and structural repairs at the Frederick Douglass Community Center Project, as an emergency procurement pursuant to Section 2-797(2) of the Code of Ordinances; Authorizing a Waiver of Code of Ordinances Section 2-845, to authorize the City Manager to allocate up to $30,000.00 of contingency allowance as necessary; Authorizing necessary budget transfers/amendments; Authorizing the City Manager to execute necessary documents.