File #: 18-2027    Version: 1 Name: Truman Waterfront Ampitheater Project Closeout
Type: Resolution Status: Passed
File created: 3/22/2018 In control: Naval Properties Local Redevelopment Authority
On agenda: 4/3/2018 Final action: 4/3/2018
Title: *Approving final Closeout Change Order 8 to D. L. Porter Constructors, Inc. in an amount not to exceed $85,843.54 for the Truman Waterfront Park Amphitheater Construction Project; Authorizing a contract time extension of 73 calendar days; Authorizing necessary budget transfers/amendments; Authorizing the City Manager to execute necessary documents upon consent of the City Attorney.
Sponsors: Jim Scholl
Attachments: 1. Resolution, 2. Executive Summary, 3. CO #8 Final, 4. CO #8 Backup, 5. Resolution 17-035

Title

*Approving final Closeout Change Order 8 to D. L. Porter Constructors, Inc. in an amount not to exceed $85,843.54 for the Truman Waterfront Park Amphitheater Construction Project; Authorizing a contract time extension of 73 calendar days; Authorizing necessary budget transfers/amendments; Authorizing the City Manager to execute necessary documents upon consent of the City Attorney.