File #: 18-3089    Version: Name:
Type: Resolution Status: Passed
File created: 10/19/2018 In control: City Commission
On agenda: 11/7/2018 Final action: 11/7/2018
Title: *Approving Change Order No. 1 from Pedro Falcon Electrical Contractors, Inc. for the ITB 18-027 Edward B. Knight Pier Lighting Project, in an amount not to exceed $10,472.00, along with a 120-day extension for contract completion; Authorizing any necessary budget adjustments; Authorizing the City Manager to execute any necessary documents, upon consent of the City Attorney.
Sponsors: Jim Scholl
Attachments: 1. Resolution, 2. Executive Summary, 3. Change Order Request, 4. ITB 18-027, 5. *Large File* Resolution 18-188, 6. Executed Contract, 7. Notice to Proceed

Title

*Approving Change Order No. 1 from Pedro Falcon Electrical Contractors, Inc. for the ITB 18-027 Edward B. Knight Pier Lighting Project, in an amount not to exceed $10,472.00, along with a 120-day extension for contract completion; Authorizing any necessary budget adjustments; Authorizing the City Manager to execute any necessary documents, upon consent of the City Attorney.