File #: 21-6973    Version: Name: Truman Waterfront Phase 1B Change Order #4
Type: Resolution Status: Passed
File created: 4/22/2021 In control: City Commission
On agenda: 5/19/2021 Final action: 5/19/2021
Title: *Approving change order #4 in the amount of $81,286.35 for additional unforeseen conditions, under the contract awarded to Charley Toppino and Sons, Inc. for Truman Waterfront Park Phase 1B; Authorizing the Interim City Manager to execute necessary documents upon advice and consent of the City Attorney; Authorizing any necessary budget transfer and amendments.
Sponsors: Patti McLauchlin
Attachments: 1. Resolution, 2. Executive Summary, 3. Change Order 1, 4. Change Order 2, 5. Res 20-070 Change Order 3, 6. TWP PH IB Contract Change Order 4, 7. Res 19-296 Truman Waterfront CTS approval

Title

*Approving change order #4 in the amount of $81,286.35 for additional unforeseen conditions, under the contract awarded to Charley Toppino and Sons, Inc. for Truman Waterfront Park Phase 1B; Authorizing the Interim City Manager to execute necessary documents upon advice and consent of the City Attorney; Authorizing any necessary budget transfer and amendments.